News · Published November 18, 2026, 8:00 p.m. EST

NEW YORK — New York City and the statewide power system face different reliability challenges in NYISO’s final 2026 Reliability Needs Assessment, dated November 17.

The study identifies a transmission-constrained need in the city beginning in summer 2032. Separately, its statewide supply assessment falls outside reliability criteria beginning in 2033.

What the projections mean

The city’s modeled summer need starts at about 400 megawatts across seven hours. The statewide deficiency starts at 225 megawatts in 2033 and grows to about 1,850 megawatts by 2036. These are separate planning measures, not quantities to add together.

NYISO links increasing risk to rising demand and reduced availability of aging generation. It says internal transmission improvements alone cannot resolve the statewide supply gap.

The New York Post covered the report November 18. Its findings are conditional planning needs that require solutions; they do not establish a schedule of future blackouts.